Brisbane's rail network, run by Queensland Rail (QR) is currently a huge mess. Since the opening of the Redcliffe Peninsula Line in early October 2016 with insufficient trains and drivers, commuters have suffered (and are continuing to suffer) from axed train services in the
Interim Timetable, as well as "random" train cancellations due to "operational reasons". The situation is so bad, that BrizCommuter is aware of many commuters who have given up using trains and have gone back to driving to work.
Between the 4th and 15th April 2018, the Gold Coast will be hosting the Commonwealth Games. At the time of writing, this is just 17 months away. BrizCommuter is very concerned that QR will not be ready for the Commonwealth Games and existing commuters will continue to suffer. The reasons why are outlined below.
Service expectations
On QR's
project page for the Coomera to Helensvale duplication, it is mentioned that the Gold Coast Line will run 8 trains per hour (tph) in both directions during the Commonwealth Games. That is a train on average every 7.5 minutes in each direction.
Lack of infrastructure
To run the above mentioned bi-directional 8tph service runs into a few issues due to lacking track infrastructure on the Gold Coast/Beenleigh Line corridor. There are only 3 tracks between Park Road and Kuraby, and only 2 tracks between Kuraby and Varsity Lakes (with a 3rd track at Bethania). This allows an 8tph service in one direction with express Gold Coast trains able to overtake slower all stations Beenleigh Line trains. But in the other direction, the Gold Coast trains are unable to overtaken the Beenleigh Line trains as they have use the same track.
To achieve the 8tph, then in one direction, Beenleigh Line trains can simply be extended to/from Varsity Lakes or Robina. Trains will alternate between express and all stations services. But in the other direction, the lack of overtaking provision will mean that the 8tph service will only be achievable by slowing down the train services, or by removing all of the slower Beenleigh Line services. Quite how this will be achieved will be unknown, but it will upset some commuters. The required timetable changes and/or system reliability may also have knock on effects on other lines during the Commonwealth Games.
A sub-optimal track layout at Varsity Lakes may also make turning back of the 8tph service unreliable and prone to delays.
BrizCommuter's twin brother asked QR's project team how this services was to be achieved, and didn't received a response.
Lack of trains
The have been insufficient trains available to run an optimal timetable since January 2014, resulting in overcrowded 3-car services in the peak. The delays to the New Generation Rollingstock (NGR) program have added to this commuter pain, with the first NGR trains not expected to be in passenger service until early 2017. This is disappointing as QR told commuters in January 2014, that the NGR would be introduced in late 2015. BrizCommuter has already worked out that
insufficient NGR trains have been ordered to cover both replacement of the geriatric EMU trains, and provide an "optimal" peak train service on all lines.
To run the Commonwealth Game's 8tph train service, then approximately 8 of these extra 6-car NGR trains will be required for this service. This means that during the Commonwealth Games, either:
- Trains lines other than the Gold Coast and Beenleigh Lines will have to experience a reduced train service (as is occurring at the moment with the Interim Timetables). This could impact passengers travelling on other train lines to connect with the extra Gold Coast Line services.
- To avoid cuts during the Commonwealth Games, QR will not improve train services on lines other than the Gold Coast and Beenleigh Lines until after the Commonwealth Games has finished. Thus for example, urgently required enhancements to the Cleveland Line pm peak service (extend express service later) and Ferny Grove Line pm peak service (fill in the gaps) may be delayed.
Both options are bad news for regular commuters.
Lack of train crew
It takes at least 12 months to train drivers (excluding recruitment phase). With the Commonwealth Games only 17 months away, that does not allow for much time to train up sufficient drivers to run both the "normal" train service (which is currently "sub-normal"), and run the "enhanced" Commonwealth Games train service. The lack of driver trainers also limits how many extra drivers can be trained. The effect on commuters is likely to be similar to the lack of train issues highlighted above.
Conclusion
Unless a miracle happens, then commuters should be very afraid that up to and during the Commonwealth Games, they may experience a sub-optimal train service from QR. The lack of accountability and transparency from QR and successive Queensland Governments only fuels BrizCommuter's concerns. Yet again, the policy failures of three successive Queensland Governments (from both sides of politics) is likely to result in yet another rail fail in April 2018.
Additionally, as the main stadium in Carrara is not directly on a train line (which is bizarre for most major sporting events), passengers using public transport to/from Brisbane will have to suffer slow and time consuming bus transfers to get to and from the trains. This will not show SE Queensland in good light.